How do I give notice that I'm pausing work for non-payment?

The short answer

Seven days, in construction. The 1996 Construction Act says you may not suspend without at least seven days' notice1 stating the ground, and only a sum notified as due and unpaid past its final date for payment2 gives you the right. Done properly, the client also owes the reasonable costs of the pause1, and time limits on the work it holds up move by the days you were stopped. Outside construction, only your contract can let you pause.

What you can add

An £18,600 stage payment, 32 days unpaid

Say you are a dry-lining subcontractor with an £18,600 stage payment notified as due. The final date for payment was Friday 18 September 2026. It is unpaid and no pay less notice came. You hand a notice to the client's site office and email it on Monday 12 October. The seven days run from 13 to 19 October, with no bank holiday in them, so you suspend from Tuesday 20 October, the earliest day the Act allows. Interest began on 19 September 2026. If your contract sets no rate of its own, the law sets one9, fixed on 30 June 202611 at 3.75% Bank Rate12 plus 8%: 11.75% a year.

£18,600.00The notified sum
£191.61Interest: £18,600 × 11.75% ÷ 365 × 32 days9
£100.00Fixed sum (debts of £10,000 or more)10
£18,891.61Owed on 20 October 2026

Then it grows by £5.99 a day until they pay. On top, the client owes the reasonable costs of the pause1. If the sum is still unpaid, the next move is adjudication.

The road ahead

Six steps. No fees.

  1. Step 1: Check the Act covers the job

    It must be a construction contract for construction operations7, and not for a home one of the parties lives in or will live in8. Otherwise only the contract's own clause decides.

    Cost: FreeTime: 5 minutes

  2. Step 2: Find the unpaid sum

    You need a notified sum. It comes from a payment notice3: theirs, or yours where the contract has you give it. If they gave none, your default notice4 sets it, and the final date for payment is pushed back by the days you left it. The sum must be unpaid after that date.

    If a valid pay less notice cut the sum, you can suspend only for what it left due.

    Cost: FreeTime: 10 minutes

  3. Step 3: Write the notice

    Use the letter below. It names section 112, states the ground, says which work stops and gives a start date. The seven days start the day after it reaches them, not the day you wrote it, and Christmas Day, Good Friday and bank holidays are left out6. Stop no sooner than the day after the seventh day; a spare day costs little.

    Cost: FreeTime: 20 minutes

  4. Step 4: Deliver it so you can prove it

    Follow the contract's notice clause first. Otherwise any effective means5 will do, and a letter posted to their registered or principal office counts as served. Hand it to the site office and email it too. Proving it arrived is its own page.

    Cost: Free, or a stampTime: Same day

  5. Step 5: On the start date, stop what the notice names

    Stop only that work. Make the site safe, take nothing away, damage nothing, and log each day and each cost as it happens.

    Cost: FreeTime: From the start date

  6. Step 6: When they pay in full, restart and claim

    The right ends1 when the notified sum is paid in full, so go back to work. Send your log. The reasonable costs of the pause1 are owed to you, and any time limit for work the pause held up moves by the days you were stopped.

    Cost: FreeTime: Same day

A letter you can copy

Notice of intention to suspend work

Send it when a notified sum is unpaid past its final date for payment, no pay less notice has cut it, and the job is a construction contract.

New email
SubjectNotice of intention to suspend under section 112:
Dear , This is a notice of intention to suspend performance under section 112 of the Housing Grants, Construction and Regeneration Act 1996. The ground: , dated , gives a sum of due to me for . The final date for payment was . That sum has not been paid in full, and I have not received a pay less notice for it. I intend to suspend from , which is more than seven days after you receive this notice. I will not suspend if the full sum has reached me before then. The right to suspend ends when the sum is paid in full, and I will resume work once it has been. Under section 112(3A) you are liable for the reasonable costs and expenses I incur because of the suspension. Under section 112(4) the days I am suspended are disregarded in counting any contractual time limit for work the suspension affects, and a date set for that work moves by the same days. I will send details of both. Interest on the late sum is also due, at the contract's rate or, if it sets none, under the Late Payment of Commercial Debts (Interest) Act 1998 with its fixed sum, and I will claim it separately. Please pay in full before to: Could you confirm the date payment will be made? If you believe any of this is wrong, please tell me before and say why. Kind regards,

Tap a highlighted gap to see what goes in it.

Hand a signed copy to the site office and email it the same day, to the address in the contract's notice clause if it has one. Keep both, with the time sent. Not a construction job? Only a suspension clause in the contract can give you the right. Send one line under it: 'Under clause 9, I give notice that I will suspend the work from 20 October 2026 unless invoice 4502 is paid in full.'

When not to bother

When it isn't worth it

  • It isn't construction work, or your client lives or will live in the home. Then only a suspension clause in your contract lets you pause. The Act excludes a contract with a residential occupier8, not a subcontract on that job.
  • A pay less notice was sent in time. The right then covers only the sum it left due. Dispute the rest through adjudication.
  • You can't point to a notified sum. With no payment notice or default notice, there is no sum for the right to rest on. Check the contract and ask a construction solicitor before you stop.
  • It's a few days late from a client who pays on time. A call costs nothing, and the notice starts a formal clock. Send it when the call has not worked.
  • Stopping would cost you more than the debt. Idle labour is a real cost. Weigh it against the sum before you name a date.

The Wolf's note

Seven days is the price of doing this properly. Put the ground in the first paragraph so a stranger could check it, count the seven days clear of bank holidays, and keep the copy. From the day it lands, the client is the one with a clock.

Mr. Wolf · the AI inside WolfX

What comes next

Your next move

All 153 answers
The two WolfX characters walk past a building site at first light with hard hats under their arms.

Don't want to do this yourself?

The Wolf does every step for you. He works out the sums, writes the letters and keeps track of every date. Nothing goes without your yes.